RoadTek Drainage and Civil Works

Concrete Drainage Installation


Project Scope: 


Culverts and drainage throughout Bowen, Proserpine and Eungella regions were installed and updated to accommodate current standards. This included the construction and installation of drains, headwalls and aprons, as well as minor repairs to concrete structures.


The addition of concrete slabs and footpaths increased the usability of the road and made it more accessible to pedestrians and cyclists. Installing lights also improved accessibility and increased safety for pedestrians and motorists.


The introduction of keystone walls ensured ____ as well as improving visual appeal


  • Concrete slabs and footpaths.
  • Keystone wall construction.
  • Electrical civil installation (conduits, pits, light pole footings)
Enquire Now
Drainage Under Construction — Hillery Group in Bowen, QLD
Road Drainage Under Construction — Hillery Group in Bowen, QLD

Staff Experience


CEO – x years

Ops Manager – 30 years on similar projects with 5 years on multiprojects

Supervisors – Fred Wallis and Elliett Hillery

Achievements


  • All vehicles and equipment compliant with RoadTek
  • Working with RoadTek employees
  • Correct traffic management and control
  • Increased safety and usability

Client, Period & Value


Client: RoadTek

Contract Period: February 2020 – May 2020

Contract Value: $441,000

Learn More

Contact Us


Client Testimony


Positive feedback from client, media or users such as residents and tourists


— source of feedback

Location

Eungella, Proserpine and Bowen areas

Contact us for any enquires

Share by: